Result: Providing and laying interlocking tiles work in village -Dyorar YEA(including construction of drain). WC-06
Awarded4 bids were received for this tender. The lowest (L1) bid is MANYA CONSTRUCTION AND SUPPLIERS's, at ₹33,97,321.73. As shown on Uttar Pradesh eProcurement on 29 Nov 2026.
Bids received (4)
- L1MANYA CONSTRUCTION AND SUPPLIERS₹33,97,321.73
Status: Accepted-AOC · Bid submitted 01-May-2025 10:59 AM · Bid no. 5158419
Remarks: L1
- L2SHUBHAM BUILDERS₹41,17,903.34
vs L1: +21% · ₹7,20,581.61 more
Status: Rejected-Finance · Bid submitted 01-May-2025 04:57 PM · Bid no. 5160378
Remarks: L2
- L3M/s R J P CONSTRUCTION₹42,62,029.95
vs L1: +25% · ₹8,64,708.22 more
Status: Rejected-Finance · Bid submitted 01-May-2025 11:38 AM · Bid no. 5154683
Remarks: L3
- L4M/S ANUSHKA CONSTRUCTION₹43,58,285.95
vs L1: +28% · ₹9,60,964.22 more
Status: Rejected-Finance · Bid submitted 01-May-2025 04:30 PM · Bid no. 5160173
Remarks: L4
Stages
- Technical Bid OpeningNot yet
- Technical EvaluationNot yet
- Financial Bid OpeningNot yet
- Financial EvaluationNot yet
- AOCNot yet
More from the portal's report
Technical Bid Opening Summary
- Type: Technical
- Summary: UNDER EVALUATION
- Updated On: 23-Jun-2025 11:11 AM
- Document: None
Technical Evaluation Summary Details
- Updated On: 24-Jun-2025 03:39 PM
- Financial Bid Opening Date: 25-Jun-2025 11:00 AM
- Document: techsummary_1865391.pdf (476.03 KB)
Finance Bid Opening Summary
- Type: Finance
- Summary: EVALUATION
- Updated On: 21-Jul-2025 05:11 PM
- Document: None
- BOQ Comparative Chart: BOQ Comparative Chart
Finance Evaluation Summary Details
- Updated on: 05-Aug-2025 04:32 PM
- Document: finsummary_1865391.pdf (531.91 KB)
AOC
- Contract Date: 05-Aug-2025
- Total Contract Value: INR 3,397,321.73
- Work Completion Period in days: 90
- Updated on: 07-Aug-2025 06:29 PM
- AOC document: AOC1044_31.pdf (809.00 KB)
- AOC Description: AOC
Questions about this result
How many bids were received for tender 2025_YEIDA_1028281_31?
4 bids were received, as shown on Uttar Pradesh eProcurement on 29 Nov 2026.
Who is the lowest bidder (L1) for "Providing and laying interlocking tiles work in village -Dyorar YEA(including construction of drain). WC-06"?
MANYA CONSTRUCTION AND SUPPLIERS, at ₹33,97,321.73. The portal shows the tender as awarded (AOC), as shown on Uttar Pradesh eProcurement on 29 Nov 2026.
Where does this result come from?
From Uttar Pradesh eProcurement's Tender Summary Report for tender ID 2025_YEIDA_1028281_31, read on 29 Nov 2026 when a visitor looked it up. Bidders are named as the portal names them.