Skip to content

Launch offer: 50% off all plans, from ₹10 a day.

See plans

Result: Clearance of Ayela Escape

Awarded12 bids were received for this tender. The lowest (L1) bid is KAMLESH KUMAR CONTRACTOR's, at ₹4,34,356.82. As shown on Uttar Pradesh eProcurement on 21 Nov 2026.

Lowest (L1), awardedKAMLESH KUMAR CONTRACTOR₹4,34,356.82 (₹4.3 lakh)

Bids received (12)

  1. L1KAMLESH KUMAR CONTRACTOR₹4,34,356.82

    Status: Accepted-AOC · Bid submitted 11-May-2026 11:00 PM · Bid no. 6108128

    Remarks: L1

  2. L2M/s Shree Dauji Enterprises₹4,63,084

    vs L1: +6.6% · ₹28,727.18 more

    Status: Rejected-Finance · Bid submitted 14-May-2026 03:03 PM · Bid no. 6115708

    Remarks: L2

  3. L3RAJKUMAR SHARMA CONTRACTOR₹4,63,270.94

    vs L1: +6.7% · ₹28,914.12 more

    Status: Rejected-Finance · Bid submitted 13-May-2026 03:11 PM · Bid no. 6103146

    Remarks: L3

  4. L4M/s R. S. Contractor & Suppliers₹4,90,981.62

    vs L1: +13% · ₹56,624.8 more

    Status: Rejected-Finance · Bid submitted 14-May-2026 04:08 PM · Bid no. 6115921

    Remarks: L4

  5. L5PUSHPENDRA KUMAR CONTRACTOR₹5,70,222.8

    vs L1: +31% · ₹1,35,865.98 more

    Status: Rejected-Finance · Bid submitted 14-May-2026 04:20 PM · Bid no. 6114330

    Remarks: L5

  6. BHAGWATIPRASAD CONTRACTOR

    Status: Rejected-Technical · Bid submitted 13-May-2026 04:12 PM · Bid no. 6113613

    Remarks: Due to Sufficient Document not Submitted

  7. chahar constructions

    Status: Rejected-Technical · Bid submitted 09-May-2026 12:50 PM · Bid no. 6100357

    Remarks: Due to Sufficient Document not Submitted

  8. CORNHILL CONSTRUCTION

    Status: Rejected-Technical · Bid submitted 14-May-2026 02:51 PM · Bid no. 6115709

    Remarks: Due to Sufficient Document not Submitted

  9. HETRAM CONSTRACTOR

    Status: Rejected-Technical · Bid submitted 10-May-2026 01:41 PM · Bid no. 6102792

    Remarks: Due to Sufficient Document not Submitted

  10. M.K. ENTERPRISES

    Status: Rejected-Technical · Bid submitted 10-May-2026 07:04 PM · Bid no. 6103651

    Remarks: Due to Sufficient Document not Submitted

  11. M/s SHASHAVEER SINGH CONTRACTOR AND SUPPLIERS

    Status: Rejected-Technical · Bid submitted 14-May-2026 11:52 AM · Bid no. 6115054

    Remarks: Due to Sufficient Document not Submitted

  12. M/S SRASHTI INFRASTRUCTURE

    Status: Rejected-Technical · Bid submitted 14-May-2026 07:16 AM · Bid no. 6114357

    Remarks: Due to Sufficient Document not Submitted

Stages

  • Technical Bid OpeningNot yet
  • Technical EvaluationNot yet
  • Financial Bid OpeningNot yet
  • Financial EvaluationNot yet
  • AOCNot yet
More from the portal's report

Technical Bid Opening Summary

  • Type: Technical
  • Summary: Admitted
  • Updated On: 18-May-2026 11:02 AM
  • Document: None

Technical Evaluation Summary Details

  • Updated On: 25-May-2026 02:20 PM
  • Financial Bid Opening Date: 26-May-2026 12:00 PM
  • Document: techsummary_2141154.pdf (301.90 KB)

Finance Bid Opening Summary

  • Type: Finance
  • Summary: Admitted
  • Updated On: 26-May-2026 05:59 PM
  • Document: None
  • BOQ Comparative Chart: BOQ Comparative Chart

Finance Evaluation Summary Details

  • Updated on: 24-Jun-2026 05:30 PM
  • Document: finsummary_2141154.pdf (328.35 KB)

AOC

  • Contract Date: 02-Jul-2026
  • Total Contract Value: INR 434,356.82
  • Work Completion Period in days: 20
  • Updated on: 02-Jul-2026 10:36 AM
  • AOC document: Aayla.pdf (328.00 KB)
  • AOC Description: Accepted

Questions about this result

How many bids were received for tender 2026_UPIDC_1145201_23?

12 bids were received, as shown on Uttar Pradesh eProcurement on 21 Nov 2026.

Who is the lowest bidder (L1) for "Clearance of Ayela Escape"?

KAMLESH KUMAR CONTRACTOR, at ₹4,34,356.82. The portal shows the tender as awarded (AOC), as shown on Uttar Pradesh eProcurement on 21 Nov 2026.

Where does this result come from?

From Uttar Pradesh eProcurement's Tender Summary Report for tender ID 2026_UPIDC_1145201_23, read on 21 Nov 2026 when a visitor looked it up. Bidders are named as the portal names them.

Trusted by contractors and suppliers across India