Result: Construction of 3 x 5.00m span box culvert replacing a damaged culvert located at Km 2 of Rura Sultanpur Road.

Awarded3 bids were received for this tender. The lowest (L1) bid is M/S VIVEK TRIPATHI & BROTHERS's, at ₹78,83,685.5. As shown on Uttar Pradesh eProcurement on 19 Nov 2026.

Lowest (L1), awardedM/S VIVEK TRIPATHI & BROTHERS₹78,83,685.5 (₹78.8 lakh)

Bids received (3)

  1. L1M/S VIVEK TRIPATHI & BROTHERS₹78,83,685.5

    Status: Accepted-AOC · Bid submitted 27-Mar-2026 11:43 PM · Bid no. 6014568

    Remarks: Financial bid is Accepted at the price of Rs. 7883685.50 by the Employer.

  2. L2M/S R A CONSTRUCTION₹82,52,584.02

    vs L1: +4.7% · ₹3,68,898.52 more

    Status: Rejected-Finance · Bid submitted 28-Mar-2026 11:54 AM · Bid no. 6008231

    Remarks: Due to L2 Rate

  3. L3M/s Churaman Contractor₹99,94,717.37

    vs L1: +27% · ₹21,11,031.87 more

    Status: Rejected-Finance · Bid submitted 28-Mar-2026 10:44 AM · Bid no. 6014784

    Remarks: Due to L3 Rate

Stages

  • Technical Bid OpeningNot yet
  • Technical EvaluationNot yet
  • Financial Bid OpeningNot yet
  • Financial EvaluationNot yet
  • AOCNot yet
More from the portal's report

Technical Bid Opening Summary

  • Type: Technical
  • Summary: Technical
  • Updated On: 28-Mar-2026 05:03 PM
  • Document: None

Technical Evaluation Summary Details

  • Updated On: 08-Apr-2026 02:16 PM
  • Financial Bid Opening Date: 08-Apr-2026 03:00 PM
  • Document: techsummary_2105932.pdf (1125.17 KB)

Finance Bid Opening Summary

  • Type: Finance
  • Summary: Finance
  • Updated On: 08-Apr-2026 04:07 PM
  • Document: None
  • BOQ Comparative Chart: BOQ Comparative Chart

Finance Evaluation Summary Details

  • Updated on: 02-Jun-2026 05:28 PM
  • Document: finsummary_2105932.pdf (1125.17 KB)

AOC

  • Contract Date: 03-Aug-2026
  • Total Contract Value: INR 7,883,685.5
  • Work Completion Period in days: 365
  • Updated on: 03-Aug-2026 12:10 PM
  • AOC document: 1.pdf (300.00 KB)
  • AOC Description: Financial bid is Accepted at the price of Rs. 7883685.50 by the Employer.

Questions about this result

How many bids were received for tender 2026_CEUCZ_1128983_1?

3 bids were received, as shown on Uttar Pradesh eProcurement on 19 Nov 2026.

Who is the lowest bidder (L1) for "Construction of 3 x 5.00m span box culvert replacing a damaged culvert located at Km 2 of Rura Sultanpur Road."?

M/S VIVEK TRIPATHI & BROTHERS, at ₹78,83,685.5. The portal shows the tender as awarded (AOC), as shown on Uttar Pradesh eProcurement on 19 Nov 2026.

Where does this result come from?

From Uttar Pradesh eProcurement's Tender Summary Report for tender ID 2026_CEUCZ_1128983_1, read on 19 Nov 2026 when a visitor looked it up. Bidders are named as the portal names them.

Trusted by contractors and suppliers across India