Result: Annual Maintenance of Unit 1 and Unit 2 3x180 540MW Hydro Generator Units of Chamera Power Station-1, Khairi, Distt. Chamba, H.P. for the year of 2025-26.

Awarded5 bids were received for this tender. As shown on Central Govt eProcurement (NIC) on 17 Nov 2026.

Bids received (5)

  1. FIBRETECH HYDRO PRIVATE LIMITED₹47,43,600

    Status: Accepted-AOC · Bid submitted 07-Nov-2025 01:59 PM · Bid no. 3313267

    Remarks: L-1 BIDDER

  2. Gogoal Hydro Pvt. Ltd.₹55,34,200

    Status: Rejected-Finance · Bid submitted 07-Nov-2025 05:48 PM · Bid no. 3312910

    Remarks: Not L-1 Bidder

  3. KKINDUSTRIES₹49,50,100

    Status: Rejected-Finance · Bid submitted 07-Nov-2025 04:30 PM · Bid no. 3313366

    Remarks: Not L-1 Bidder

  4. SHARMA LIGHT HOUSE

    Status: Rejected-Technical · Bid submitted 08-Nov-2025 12:44 PM · Bid no. 3310857

    Remarks: Technically Not Qualified

  5. SINE HYDRO PRIVATE LIMITED₹53,40,000

    Status: Rejected-Finance · Bid submitted 08-Nov-2025 12:37 PM · Bid no. 3313278

    Remarks: Not L-1 Bidder

Stages

  • Technical Bid OpeningNot yet
  • Technical EvaluationNot yet
  • Financial Bid OpeningNot yet
  • Financial EvaluationNot yet
  • AOCNot yet
More from the portal's report

Technical Bid Opening Summary

  • Type: Technical
  • Summary: Bid Opening Summary
  • Updated On: 22-Nov-2025 03:45 PM
  • Document: technical_927952.pdf

Technical Evaluation Summary Details

  • Updated On: 22-Nov-2025 04:02 PM
  • Financial Bid Opening Date: 22-Nov-2025 04:30 PM
  • Document: techsummary_927952.pdf (770.56 KB)

Finance Bid Opening Summary

  • Type: Finance
  • Summary: Bid Opening Summary
  • Updated On: 24-Nov-2025 04:48 PM
  • Document: finance_927952.pdf
  • BOQ Comparative Chart: BOQ Comparative Chart

Finance Evaluation Summary Details

  • Updated on: 24-Dec-2025 04:32 PM
  • Document: finsummary_927952.pdf (199.58 KB)

AOC

  • Contract Date: 24-Dec-2025
  • Total Contract Value: INR 6,488,490
  • Work Completion Period in days: 42
  • Updated on: 24-Dec-2025 04:38 PM
  • AOC document: LOA.pdf (8761.00 KB)
  • AOC Description: Annual Maintenance of Unit 1 and Unit 2 3x180 540MW Hydro Generator Units of Chamera Power Station-1, Khairi, Distt. Chamba, H.P. for the year of 2025-26.

Questions about this result

How many bids were received for tender 2025_NHPC_882879_1?

5 bids were received, as shown on Central Govt eProcurement (NIC) on 17 Nov 2026.

Where does this result come from?

From Central Govt eProcurement (NIC)'s Tender Summary Report for tender ID 2025_NHPC_882879_1, read on 17 Nov 2026 when a visitor looked it up. Bidders are named as the portal names them.

Trusted by contractors and suppliers across India