Result: Providing and fixing of road signage, security signage and shuttle stop board at various locations inside, BARC, Mumbai.
Awarded9 bids were received for this tender. The lowest (L1) bid is MANOJ CONSTRUCTIONS's, at ₹1,26,96,850. As shown on Central Govt eProcurement (NIC) on 16 Nov 2026.
Bids received (9)
- L1MANOJ CONSTRUCTIONS₹1,26,96,850
Status: Accepted-AOC · Bid submitted 17-Dec-2025 02:59 PM · Bid no. 3334993
Remarks: Being L1
- L2Jayesh Prakash Sawant₹1,29,29,750
vs L1: +1.8% · ₹2,32,900 more
Status: Rejected-Finance · Bid submitted 17-Dec-2025 02:44 PM · Bid no. 3334576
Remarks: Not being L1
- L3Shivkrupa Enterprises₹1,29,50,350
vs L1: +2.0% · ₹2,53,500 more
Status: Rejected-Finance · Bid submitted 16-Dec-2025 05:47 PM · Bid no. 3334528
Remarks: Not being L1
- L4shoiab construction₹1,29,81,500
vs L1: +2.2% · ₹2,84,650 more
Status: Rejected-Finance · Bid submitted 16-Dec-2025 01:33 PM · Bid no. 3334304
Remarks: Not being L1
- L5lalit constructions₹1,31,49,850
vs L1: +3.6% · ₹4,53,000 more
Status: Rejected-Finance · Bid submitted 17-Dec-2025 10:12 AM · Bid no. 3334758
Remarks: Not being L1
- L6ANUBHAV ENGINEERING COMPANY₹1,34,02,700
vs L1: +5.6% · ₹7,05,850 more
Status: Rejected-Finance · Bid submitted 17-Dec-2025 02:46 PM · Bid no. 3335002
Remarks: Not being L1
- L7Shree Enterprises₹1,38,92,400
vs L1: +9.4% · ₹11,95,550 more
Status: Rejected-Finance · Bid submitted 16-Dec-2025 02:54 PM · Bid no. 3334389
Remarks: Not being L1
- L8SUNIL CONSTRUCTION₹1,43,54,000
vs L1: +13% · ₹16,57,150 more
Status: Rejected-Finance · Bid submitted 17-Dec-2025 10:59 AM · Bid no. 3334786
Remarks: Not being L1
- L9MARUTI ENTERPRISES₹1,48,23,300
vs L1: +17% · ₹21,26,450 more
Status: Rejected-Finance · Bid submitted 17-Dec-2025 02:31 PM · Bid no. 3334928
Remarks: Not being L1
Stages
- Technical Bid OpeningNot yet
- Technical EvaluationNot yet
- Financial Bid OpeningNot yet
- Financial EvaluationNot yet
- AOCNot yet
More from the portal's report
Technical Bid Opening Summary
- Type: Technical
- Summary: Nine EMD Received and Nine accepted.
- Updated On: 19-Dec-2025 04:29 PM
- Document: None
Technical Evaluation Summary Details
- Updated On: 14-Jan-2026 12:27 PM
- Financial Bid Opening Date: 16-Jan-2026 03:30 PM
- Document: techsummary_930961.pdf (381.93 KB)
Finance Bid Opening Summary
- Type: Finance
- Summary: Nine bids are accepted and sent for Financial Evaluation
- Updated On: 16-Jan-2026 05:09 PM
- Document: None
- BOQ Comparative Chart: BOQ Comparative Chart
Finance Evaluation Summary Details
- Updated on: 05-Feb-2026 05:21 PM
- Document: finsummary_930961.pdf (362.07 KB)
AOC
- Contract Date: 21-May-2026
- Total Contract Value: INR 12,696,850
- Work Completion Period in days: 365
- Updated on: 07-May-2026 06:27 PM
- AOC document: WOET56.pdf (4275.00 KB)
- AOC Description: Wo issued
Questions about this result
How many bids were received for tender 2025_BARC_885695_1?
9 bids were received, as shown on Central Govt eProcurement (NIC) on 16 Nov 2026.
Who is the lowest bidder (L1) for "Providing and fixing of road signage, security signage and shuttle stop board at various locations inside, BARC, Mumbai."?
MANOJ CONSTRUCTIONS, at ₹1,26,96,850. The portal shows the tender as awarded (AOC), as shown on Central Govt eProcurement (NIC) on 16 Nov 2026.
Where does this result come from?
From Central Govt eProcurement (NIC)'s Tender Summary Report for tender ID 2025_BARC_885695_1, read on 16 Nov 2026 when a visitor looked it up. Bidders are named as the portal names them.