Result: Tiling work in the upgraded hostel at Kasturba Gandhi Balika Vidyalaya, Moth, in District Jhansi

Awarded7 bids were received for this tender. The lowest (L1) bid is M/S ANUPAL SINGH's, at ₹1,69,904.26. As shown on Uttar Pradesh eProcurement on 16 Nov 2026.

Lowest (L1), awardedM/S ANUPAL SINGH₹1,69,904.26 (₹1.7 lakh)L1 was 92% below the estimate of ₹20,00,000

Bids received (7)

  1. L1M/S ANUPAL SINGH₹1,69,904.26

    Status: Rejected-Finance · Bid submitted 16-Oct-2026 04:24 PM · Bid no. 6673697

    Remarks: Rejected by Lottery

  2. L1M/S PARASHURAM CONSTRUCTION₹1,69,904.26

    Status: Rejected-Finance · Bid submitted 22-Oct-2026 07:55 AM · Bid no. 6693497

    Remarks: Rejected by Lottery

  3. L1SAURABH CONSTRUCTION₹1,69,904.26

    Status: Rejected-Finance · Bid submitted 21-Oct-2026 08:36 PM · Bid no. 6691688

    Remarks: Rejected by Lottery

  4. L1SUNIL KUMAR BHATT₹1,69,904.26

    Status: Accepted-AOC · Bid submitted 21-Oct-2026 04:40 PM · Bid no. 6691826

    Remarks: Selected through Lottery

  5. L1SUNIL KUMAR SHIVHARE₹1,69,904.26

    Status: Rejected-Finance · Bid submitted 22-Oct-2026 08:23 AM · Bid no. 6693538

    Remarks: Rejected by Lottery

  6. L2RAJPOOT CONSTRUCTION COMPANY₹19,99,487.39

    vs L1: +1077% · ₹18,29,583.13 more

    Status: Rejected-Finance · Bid submitted 21-Oct-2026 07:14 PM · Bid no. 6692329

    Remarks: Not Qualified

  7. L3APRAJIT CONSTRUCTION₹19,99,687.38

    vs L1: +1077% · ₹18,29,783.12 more

    Status: Rejected-Finance · Bid submitted 21-Oct-2026 08:01 PM · Bid no. 6692665

    Remarks: Not Qualified

Stages

  • Technical Bid OpeningNot yet
  • Technical EvaluationNot yet
  • Financial Bid OpeningNot yet
  • Financial EvaluationNot yet
  • AOCNot yet
More from the portal's report

Technical Bid Opening Summary

  • Type: Technical
  • Summary: Summary
  • Updated On: 22-Oct-2026 02:56 PM
  • Document: None

Technical Evaluation Summary Details

  • Updated On: 26-Oct-2026 12:53 PM
  • Financial Bid Opening Date: 26-Oct-2026 01:10 PM
  • Document: techsummary_2261259.pdf (7742.58 KB)

Finance Bid Opening Summary

  • Type: Finance
  • Summary: Summary
  • Updated On: 26-Oct-2026 02:23 PM
  • Document: None
  • BOQ Comparative Chart: BOQ Comparative Chart

Finance Evaluation Summary Details

  • Updated on: 29-Oct-2026 12:50 PM
  • Document: finsummary_2261259.pdf (166.67 KB)

AOC

  • Contract Date: 29-Oct-2026
  • Total Contract Value: INR 1,699,904.26
  • Work Completion Period in days: 60
  • Updated on: 29-Oct-2026 12:56 PM
  • AOC document: Moth.pdf (167.00 KB)
  • AOC Description: AOC

Questions about this result

How many bids were received for tender 2026_CEJNS_1196883_12?

7 bids were received, as shown on Uttar Pradesh eProcurement on 16 Nov 2026.

Who is the lowest bidder (L1) for "Tiling work in the upgraded hostel at Kasturba Gandhi Balika Vidyalaya, Moth, in District Jhansi"?

M/S ANUPAL SINGH, at ₹1,69,904.26. The portal shows the tender as awarded (AOC), as shown on Uttar Pradesh eProcurement on 16 Nov 2026.

Where does this result come from?

From Uttar Pradesh eProcurement's Tender Summary Report for tender ID 2026_CEJNS_1196883_12, read on 16 Nov 2026 when a visitor looked it up. Bidders are named as the portal names them.