Work order format for government contracts: letter of acceptance, agreement and sample formats

Work order format for government works: what an LoA and work order contain, CPWD and central timelines, and three sample formats you can adapt and check.

By GovtTenderHub editorial teamUpdated 14 min read

On this page

In short

  • A work order is the department's written instruction to start a contract. It usually follows a letter of acceptance (LoA), also called a letter of award or letter of intent, which tells you your bid has been accepted.
  • Under the central works manual, the LoA forms the contract, subject only to your giving performance security, generally within 14 to 28 days. For contracts up to ₹10 lakh the LoA can be the whole contract; above that a contract document is signed.
  • The work order to commence should be issued within about 2 weeks, and not later than 6 weeks, of the LoA.
  • In CPWD, the date of start is 3 to 10 days from the letter of intent, the performance guarantee is due within 7 days (extendable by up to 7 more), and the agreement is signed within 15 days of the stipulated start date.
  • A good work order names the work, the agreement amount, the start date, time for completion, the site and the securities you owe. Our sample formats below show each part.
  • Keep every LoA and work order: with a completion certificate, it is your proof of experience in later tenders.

A work order format is what you need when you are about to issue a contract or check one you have just received. In government works, the papers come in a set order: a letter of acceptance, then the agreement, then a work order telling you to start. This guide explains what each one means under the central works manual and CPWD's contract conditions, what a work order should contain, and gives sample formats written for this site.

What is a work order?

A work order is a written order from the buyer telling a contractor to carry out a stated piece of work on stated terms. In government buying the word is used in two ways:

  • As the contract itself. The Department of Expenditure's Manual for Procurement of Works 2025 (the central works manual) lists "Work Order" among the names a contract can carry, alongside purchase order, letter of award and agreement (definition 13).
  • As the order to commence. Once the contract is signed and the performance security is in, the contract manager issues a "Work Order" to the contractor to commence the works (para 7.2.4).

On GeM the contract for goods and services is the purchase order the portal generates, as our tender terms glossary explains. In works, you'll meet three papers:

PaperWhat it doesWho signs
Letter of acceptance (LoA)Tells you your bid is accepted and asks for performance securityThe accepting officer
Contract agreementPuts all the tender papers, your offer and the LoA together as one contractBoth sides
Work order (letter to commence)Tells you to start, from a date, at a named siteThe Engineer-in-Charge or contract manager

Small contracts may combine these into one letter. Large ones keep them apart.

Letter of acceptance (LoA): when the contract is formed

The central works manual calls it the "Letter of Award" and says it is also known as the letter of intent or notification of award: the letter that tells the contractor its bid has been accepted (definition 28).

Under para 6.5.1 of the manual:

  1. The LoA is sent before the bid validity ends, by registered letter or another method that gives proof of delivery, with brief details such as prices and specification.
  2. The same letter asks for performance security within a set period, "generally 14 (fourteen) to 28 (twenty-eight) days, depending upon the amount". See performance security in tenders.
  3. The LoA forms the contract. The manual says it "shall constitute the legal formation of the contract, subject only to the furnishing of performance security". The buyer may also skip the LoA and issue the contract directly.
  4. Up to ₹10 lakh, where the tender included the general and special conditions and the scope of work, the LoA itself results in a binding contract.
  5. Above ₹10 lakh, a contract document is executed. If the tender papers were complete, this can be a simple one-page contract with the conditions, scope, your offer and the LoA attached.
  6. Turnkey works and maintenance agreements always need a contract document.
  7. The contract value includes taxes, duties and levies.

The manual's Annexure 8 gives a template for the LoA. It tells the bidder it has been selected, states the contract price, gives a date to sign the contract and a date to submit performance security.

Acceptance in CPWD contracts

CPWD tenders use its standard forms: Form 7 for percentage rate tenders, where you quote above or below the estimated cost, and Form 8 for item rate tenders, where you quote a rate for each item (CPWD Works Manual 2026). The bottom of the form has an Acceptance block. The accepting officer fills in the accepted sum, signs "for and on behalf of the President of India", and lists any letters that will form part of the contract, such as letters in which you clarified or changed your offer.

CPWD's General Conditions of Contract (GCC) 2023 define the contract as the tender documents and their acceptance, the formal agreement, and the documents it refers to, including the conditions, specifications, drawings and the Engineer-in-Charge's instructions, all read together as one contract.

What a work order or LoA should contain

Whether you issue one or receive one, check for these:

  • Reference numbers: the tender or NIT number, your bid reference and the date bids were opened.
  • Name of work and location, exactly as in the tender.
  • Your firm's name and address, as in your bid.
  • The accepted amount in figures and words, and whether it includes GST. Under CPWD's GCC the "tendered value" is the value of the whole work as stated in the letter of award.
  • Performance security: amount, form and the date it is due.
  • Signing of the agreement: where and by when.
  • Date of start, or how it is worked out, and the time for completion.
  • Site details: when and how the site will be handed over.
  • Documents you must give before starting: work programme, labour registrations, names of your technical staff.
  • Any letters forming part of the contract, such as clarifications you gave during evaluation.
  • Name, designation and signature of the issuing officer, with office address and contact details.

Work order format (sample)

These samples are our own, written to cover the points above. A department should use its own standard form where it has one, and a contractor should accept whatever format the buyer issues; use these to check nothing is missing.

Sample 1: letter of acceptance

[Letterhead of the department / office]

No. ……………… Date: ………………

To M/s ……………… (name and address as in the bid)

Subject: Acceptance of your bid for ……………… (name of work)

Reference: NIT / tender no. ……………… ; your bid ID ……………… ; bids opened on ……………… .

  1. Your bid for the above work is accepted for ₹ ……………… (in words: ………………), inclusive of GST / other taxes as stated in the tender. The following letters form part of the contract: (a) ……………… (b) ……………… .
  2. Please submit performance security of ₹ ……………… in one of the forms allowed in the tender by ……………… . If it is not received in time, action will follow as per the tender conditions.
  3. Please attend this office to sign the agreement by ……………… .
  4. The date of start will be ……………… / will be the date of handing over of the site, whichever is later. The time allowed for completion is ……… months from the date of start.
  5. Before starting, please submit: work programme, names and qualifications of your technical staff, and the labour registrations required by the contract.

(Signature) Name and designation of the accepting officer Office address, phone and official email

Copy to: Engineer-in-Charge / accounts office, for information.

Sample 2: work order (letter to commence work)

[Letterhead of the department / office]

No. ……………… Date: ………………

To M/s ………………

Subject: Work order to commence ……………… (name of work), agreement no. ………………

  1. Your performance security of ₹ ……………… (form and number ………………) has been received, and agreement no. ……………… dated ……………… has been signed.
  2. You are directed to commence the work from ……………… . The site at ……………… (location) will be handed over on that date by ……………… (officer). Portions not free of hindrance will be handed over as stated in the agreement.
  3. The stipulated date of completion is ……………… .
  4. The work will be done as per the agreement, specifications and drawings, and the instructions of the Engineer-in-Charge.
  5. Please report to the Engineer-in-Charge with your approved work programme and keep the site order book at site.

(Signature) Engineer-in-Charge, with name, designation and office address

Sample 3: contractor's reply on receiving an LoA

[Contractor's letterhead]

Date: ………………

To ……………… (issuing officer)

Subject: Acknowledgement of letter of acceptance no. ……………… dated ………………

We acknowledge receipt of your letter of acceptance for ……………… (name of work) for ₹ ……………… . We confirm that we will submit the performance security by ……………… and sign the agreement by ……………… . Our authorised representative for this work is ……………… (name, phone, email), and our principal technical representative is ……………… (name and qualification).

(Signature) Name and designation, for M/s ………………

What to do after you receive a letter of acceptance

The clock starts on the date of the letter, so act the same day.

  1. Read the LoA against your bid. Check the amount, the name of work and any letters it lists as part of the contract. Raise a mistake in writing at once.
  2. Arrange performance security. Ask your bank for the guarantee in the buyer's exact format; see bank guarantee for tender. Missing the deadline is costly: in CPWD, if you don't give it within the set period, your earnest money is forfeited automatically and you can't bid when the work is re-tendered (CPWD Works Manual 2026, para 5.1.7).
  3. Name your people. CPWD's GCC asks you, immediately after the LoA and before starting, to give the Engineer-in-Charge the names, qualifications and experience of your principal technical representative and site engineers. The Engineer-in-Charge replies within 3 days (Clause 32).
  4. Prepare the programme and labour papers. CPWD's Schedule F lists, with the performance guarantee, the programme chart and the labour licences and registrations with EPFO, ESIC and the building workers' welfare board, or proof that you have applied.
  5. Sign the agreement on the date given.
  6. Take over the site and start. Under the central manual, the contract manager visits the site with you before issuing the work order, and you submit your work programme, method statement and quality assurance plan (para 7.2.4).

CPWD timelines at a glance

StepCPWD ruleSource
Performance guaranteeWithin the days set by the NIT approving authority, not beyond 7 days of the letter of intent; extendable by up to 7 more days with interestWorks Manual 2026, para 5.2
Date of start3 to 10 days from the letter of intent, or the date the site is handed over if laterWorks Manual 2026, para 5.3; GCC 2023
Letter to commenceIssued only after an acceptable performance guaranteeWorks Manual 2026, para 5.3
Agreement signedWithin 15 days of the stipulated date of startGCC 2023, signing of contract (para 9)

GCC 2023's own Schedule F leaves the number of days for the performance guarantee to the NIT approving authority (anywhere from 1 to 15) and allows a late fee of 0.1% of the guarantee amount per day for the extension period. The 2026 manual is newer and tighter, so read Schedule F of your tender for the figure that binds you.

CPWD's performance guarantee is 5% of the estimated cost put to tender or the contract amount, whichever is higher, and stays valid at least six months beyond the completion of all contractual obligations (Works Manual 2026, para 5.2). If your bid is below 80% of the estimate, you also give an additional guarantee.

The contract agreement: what it includes

The agreement pulls every paper into one contract. Under CPWD's GCC 2023 (para 9), the contractor signs a contract made up of:

  • the notice inviting tender and all tender documents and drawings as issued, the acceptance, and any correspondence leading to it;
  • the standard CPWD form named in Schedule F, with its clauses and corrections up to the date stated;
  • the CPWD Safety Code, the model rules for workers' health and sanitation, the CPWD Contractor's Labour Regulations, and the list of acts and omissions for which fines can be imposed.

No payment is made for work done until the contract is signed. Each page of the agreement is signed by the Engineer-in-Charge and the contractor, and you get one copy free; extra copies are charged at ₹2,000 each or as the NIT approving authority decides (CPWD Works Manual 2026, para 5.4.1).

The central works manual (para 6.5.5) adds that every contract must provide for liquidated damages for delay, a defect liability or warranty clause for works above a threshold, payment of all taxes by the contractor, and how the start date is fixed. Contracts likely to run more than two years should, where feasible, let the government revoke them on six months' notice. Our guides on liquidated damages and the defect liability period explain those clauses.

Work orders as proof of experience

Most works tenders ask you to prove similar work with work orders or agreements plus completion certificates from the same buyers. The work order shows what you were given and for how much; the completion certificate shows you finished it. Our documents checklist and work completion certificate guides explain what evaluators look for.

So file every LoA, agreement and work order by type of work, with the agreement number and value easy to find. When you later bid, the agreement number on the completion certificate should match the work order you upload.

If you issue work orders to sub-contractors

Your own work orders to sub-contractors and suppliers should carry the same parts: the work, the price, the dates and the payment terms. Remember that in a CPWD contract you can't sublet the work without the Engineer-in-Charge's written approval (GCC 2023, Clause 21).

Common mistakes with work orders

  • Not checking the amount. A typing error in the accepted sum becomes a dispute at the final bill.
  • Ignoring the letters listed in the acceptance. They are part of your contract.
  • Sub-letting without approval. In CPWD it lets the department act under Clause 3, which deals with ending the contract.

Once your paperwork is in order, look for the next job among CPWD tenders and other civil works tenders on GovtTenderHub.

Common questions

What is a work order in a government contract?

It is the department's written order to carry out a contract. The word covers both the contract itself and the letter telling you to commence work, which the central works manual says should follow within about two weeks, and not later than six weeks, of the letter of acceptance.

What is the difference between a letter of acceptance and a work order?

The letter of acceptance tells you your bid has been accepted and asks for performance security; under the central works manual it forms the contract. The work order comes after the agreement is signed and the security is in, and tells you to start work at the site.

Is a letter of intent the same as a letter of acceptance?

In central government works, yes in effect. The central works manual treats "letter of intent" and "notification of award" as other names for the letter of award, and CPWD's manual uses "letter of intent" for the letter from which the start date and performance guarantee are counted.

What should a work order contain?

The tender and agreement references, name and location of work, your firm's name, the accepted amount, the date of start and time for completion, the site handover details, the securities due and the issuing officer's signature and designation.

How many days after the letter of acceptance must I give performance security?

Generally 14 to 28 days under the central manuals, depending on the amount. CPWD allows no more than 7 days, extendable by up to 7 more with interest. Your tender states the exact period.

Can I use a work order as experience proof without a completion certificate?

Usually not. Tenders want completed work, so they ask for the work order or agreement together with a completion certificate showing the value and completion date.

Find tenders. Win them. Run the work.

  • Alerts, ₹299 a month: New tenders for your work by email every morning, anywhere in India, and full details of every tender.
  • Business, ₹599 a month: Alerts, plus who bid and who won each tender, GST bills, letters on your letterhead and workers' wages.

Searching tenders is free. Prices include GST; pay yearly and save 10%.

All guides

Trusted by contractors and suppliers across India