RA bill full form: what a running account bill is, its format and deductions

RA bill full form is running account bill. See what an RA bill means in construction, a running bill format, the deductions and a worked example.

By GovtTenderHub editorial teamUpdated 14 min read

On this page

In short

  • RA bill full form: Running Account bill. Also called a running bill, R/A bill or interim bill, it pays you for the work done so far on a works contract.
  • It is an advance, not a final settlement. CPWD's contract calls interim payments "payment by way of advances against final payment only". Quantities can be corrected in a later bill.
  • It comes from the measurement book (MB): checked quantities × agreement rates, minus what earlier bills already covered.
  • CPWD pays running bills monthly on works costing over ₹20 lakh: at least 75% within 10 working days and the rest within 28 working days. Works of ₹20 lakh or less are paid only after completion.
  • Usual deductions: income-tax TDS (Section 393, old Section 194C), 2% GST TDS, security deposit (CPWD: 2.5% of each bill), labour cess, and recoveries of advances or for delay.
  • The final bill closes the contract. In CPWD, submit it within 3 months of physical completion or 1 month of the final completion certificate, whichever is earlier. No new claims after that.

The RA bill full form is running account bill: the bill a contractor raises every month or so for the work measured to date, long before the job is finished. On government civil, electrical or road work, your cash flow depends on these bills. This guide explains what an RA bill means, how it is prepared, how fast it is paid, what is deducted and how the final bill differs, with a running bill format and a worked example.

RA bill full form and meaning

RA stands for running account. The department keeps one account open with you for the whole contract. Each bill adds the work done since the last one and pays for it, less deductions. Bills are numbered in order (1st RA bill, 2nd RA bill...) and the last one is the final bill.

You'll see other names for it: running bill, R/A bill, interim or intermediate bill (the words in Clause 7 of CPWD's General Conditions of Contract, GCC 2023), and on-account bill.

So what is an RA bill in construction? A part payment for work actually done and measured. Money for work not yet done, like a mobilisation advance, is a different thing, and it is recovered from your bills later.

An RA bill is an advance against the final bill

This is the key point. CPWD's Clause 7 says: "All such interim payments shall be regarded as payment by way of advances against final payment only." Any certificate behind a running payment "may be modified or corrected by any subsequent such certificate(s) or by the final certificate", and doesn't prove that the work meets the specifications. In plain words:

  • A quantity paid in RA bill 3 can be cut in RA bill 5 or the final bill if a later check finds it over-measured.
  • Payment doesn't mean acceptance. Bad work can still be rejected and has to be redone.

How an RA bill is prepared: the measurement book

Every running bill starts in the measurement book (MB), the official record of the quantity of each item done. CPWD now uses a computerised or electronic measurement book (CMB or EMB) on its ERP portal. GCC Clause 6 sets the routine:

  1. You enter the measurements of every item with financial value, on A-4 pages in the department's format.
  2. The department checks them. With an EMB, you raise a Request for Inspection (RFI) online, and the Engineer-in-Charge's team checks it and sends back anything to correct.
  3. You submit a clean, bound copy with machine-numbered pages. No cutting or overwriting is allowed; an error means a fresh MB.
  4. The bill is worked out: checked quantity × agreement rate = value of work done to date. Subtract the value up to the last RA bill to get this bill.
  5. You submit the bill "on the format of the Department in triplicate" by the date fixed each month (Clause 7).

If the department refuses an item you claim, ask for it to be measured anyway. The CPWD Works Manual 2026 (para 5.12.3) asks officers to record such items "without prejudice", so the quantities are on record if the claim goes to arbitration or court.

How often RA bills are paid

Your contract decides. Under CPWD's GCC Clause 7:

  • Works estimated at ₹20 lakh or less: no payment until the whole work is complete and certified. One bill covers the job: a first and final bill.
  • Works over ₹20 lakh: running bills each month, on the date the Engineer-in-Charge fixes.
  • Minimum bill value: Schedule F of your contract sets the minimum work done since the last payment. Below it, the bill waits for the next monthly date.
StepCPWD time limit
At least 75% of the net bill (ad-hoc)10 working days from submission
The rest, after final checking28 working days from submission
Interest if unpaid and the bill is in order5% a year simple, after 45 days

If the 75% isn't paid in 10 working days, the Works Manual 2026 (para 5.18.1) says it must be paid as soon as possible, and the Executive Engineer must then explain the delay in writing to the next higher authority within three working days. The Department of Expenditure's Manual for Procurement of Works 2025, used by other central buyers, has the same 75%-in-10 and rest-in-28 working days rule, with interest at the GPF rate after 30 working days where the contract provides for it.

CPWD can also pay before full measurement. On your request, work done but not yet measured or checked can be paid as a lump-sum advance on Form CPWA 26 (Works Manual para 5.12.5). And under Clause 7, each floor's work up to lintel and slab level can be paid at 75% of its assessed value without detailed measurement. You must adjust it in your next bill within 10 days, or pay simple interest at 10% a year.

What is deducted from an RA bill

These are the common deductions in central works. Your contract and the department's bill memo show the exact ones.

Income-tax TDS. From 1 April 2026, TDS on contractors falls under Section 393(1) of the Income-tax Act, 2025, table item 6(i) (old Section 194C). The Income Tax Department says the rates and limits are the same under both Acts. Which law applies depends on the earlier of credit or payment: on or before 31 March 2026, the 1961 Act; on or after 1 April 2026, the 2025 Act. The department's bill memo shows the amount deducted. The tax shows in your annual tax statement: Form 26AS up to 2025-26, Form 168 from tax year 2026-27.

GST TDS. Government departments deduct 2% GST TDS on a contract whose taxable value is over ₹2.5 lakh, worked out on the value before GST. The Works Manual (para 5.18.5) says GST is deducted "as per the GST Act". It reaches you as a credit on the GST portal once the department files its TDS return; see GST TDS on government contracts.

Security deposit or retention. CPWD deducts 2.5% of the gross amount of each running and final bill until it reaches 2.5% of the tendered amount (GCC Clause 1A). The central works manual says usually 5% of each bill. See our retention money guide for refunds and bank guarantees.

Labour welfare cess. The Building and Other Construction Workers Welfare Cess Act, 1996 levies a cess on the cost of construction. CPWD's GCC (Clause 33) makes it payable by the contractor, and CPWD's rate analysis adds 1% cess to its rates (see schedule of rates). Many departments deduct it from each bill.

Recoveries of advances. CPWD can pay a secured advance of up to 75% of the assessed value of non-perishable materials brought to site, recovered from the next bill once they are used (Clause 10B). A mobilisation advance of up to 10% of the tendered amount is recovered from bills, with interest, starting after 10% of the work is billed and finishing by 80%. Materials, water or electricity supplied by the department are recovered too, as your contract says.

Delay and price variation. Liquidated damages are usually recovered from running and final bills; see liquidated damages in a contract. A price variation clause can add to or reduce a bill, and the works manual asks you to submit its calculation with each bill, even when it is zero.

RA bill format (running bill format)

There is no single national form, so use your department's. Most running bills have three parts.

Part 1, the heading: name and location of work; agreement or work order number and date; your name, PAN and GSTIN; RA bill number and period; MB or e-MB number, pages and date of measurement; tendered amount, start date and stipulated completion date.

Part 2, items of work up to date:

Item (unit)Qty to dateRate (₹)Amount (₹)
Earthwork in excavation (cum)1,0003003,00,000
PCC 1:4:8 (cum)1006,0006,00,000
RCC, foundations and columns (cum)2509,60024,00,000
Steel reinforcement (kg)9,0001009,00,000
Value of work done to date42,00,000

Part 3, this bill, deductions and net payable, as in the example below.

Running bill example: a worked RA bill

A partnership firm has a ₹1 crore building contract on CPWD-style terms. This is its 3rd RA bill. Rates are taken before GST to keep the sums simple. (In CPWD, tendered rates already include GST, and your tax invoice shows the GST part.)

LineAmount (₹)
Value of work done to date42,00,000
Less: value in RA bills 1 and 232,00,000
Value of this bill (A)10,00,000
DeductionHow worked outAmount (₹)
GST TDS2% of value before GST20,000
Security deposit2.5% of the bill25,000
Labour cess1% of the bill10,000
Secured advance recovered75% of ₹80,000 steel, now used60,000
Total deductions (B)1,15,000
Net before income-tax TDS (A − B)plus GST on your invoice8,85,000
  • Income-tax TDS comes off as well, under Section 393 (old 194C). The bill memo shows it. It is set against the firm's income tax for the year.
  • The ₹20,000 GST TDS isn't lost either. It becomes a credit in the firm's GST cash ledger once accepted on the portal.
  • The ₹25,000 is still the firm's money, held until refund. Deductions stop once ₹2.5 lakh (2.5% of ₹1 crore) is held.
  • The ₹60,000 was paid in RA bill 2 as secured advance on steel at site. The steel is now used, so it is taken back.
  • Timing: at least 75% of the net bill should arrive within 10 working days of a complete bill, the rest within 28.

Contractor bill format and labour contractor bill format

A sub-contractor or labour contractor bills the main contractor the same way, only simpler. At the top: bill number and date, your name, address and PAN (and GSTIN if registered), the main contractor, and the work, site and period.

Work (unit)QtyRate (₹)Amount (₹)
Brickwork, labour only (cum)1201,2001,44,000
Plastering, labour only (sqm)8009072,000
Total2,16,000

For gang labour paid by the day, use days × daily rate for each trade. Show advances already received, and get the site engineer to sign the measurements or attendance. If you're registered for GST, issue a proper tax invoice. The main contractor may deduct income-tax TDS from your bill; ask for the TDS certificate and check the amount in your annual tax statement.

Why RA bills get stuck

  1. Labour papers missing. CPWD's Clause 7A: "No Running Account Bill shall be paid" until your labour licences and EPFO, ESIC and BOCW Welfare Board registrations, as applicable, are submitted. Hand them in at the start.
  2. RFIs not inspected. Raise them as work progresses, not on billing day.
  3. Errors in the MB. Cutting or overwriting means a fresh MB.
  4. Below the Schedule F minimum. A small month rolls over to the next billing date.
  5. Extra or deviated items not sanctioned. Their rates are fixed under GCC Clause 12. Ask early; the Works Manual (para 5.11) asks authorities to sanction them within the GCC's time limits.
  6. Bills not submitted. Under Clause 7, if you don't submit bills, "no claims whatsoever due to delays on payment including that of interest" are payable to you.

A pending extension of time is no reason to stop billing: Clause 7 says interim payments "shall continue to be made" while it is considered. If a bill is late, write to the Engineer-in-Charge with the bill number and submission date, quote the time limits, and keep copies.

The final bill (and the first and final bill)

The final bill settles everything: final quantities, extra items, deviations, price variation and recoveries. Under CPWD's GCC Clause 9:

  • Submit it within three months of physical completion or one month of the final completion certificate, whichever is earlier.
  • No claims after it. Anything not claimed by then is "deemed to have been waived and extinguished".
  • Payment is due within three months of the department receiving the complete bill, with 5% a year simple interest after that if you submitted on time and the bill is in order.

Before paying, CPWD needs sanctioned extra items and deviations, escalation and recovery statements, the theoretical statement of materials, the final completion certificate, the sanctioned final extension of time, the mandatory tests statement and the dismantled materials account (Works Manual para 5.18.1).

Running (RA) billFinal bill
What it isAdvance for work measured so farFinal settlement
QuantitiesCan be corrected laterFinal
CPWD payment time75% in 10 working days, rest in 28Within 3 months of a complete bill
New claimsStill possibleNone after you submit it

A first and final bill is one bill that is both first and last, common on small works and the rule in CPWD for works of ₹20 lakh or less. In CPWD, your security deposit isn't refunded until the final bill is passed (retention money). When you ask for a work completion certificate, attach the final bill: the certificate quotes the value of work done.

Keeping track of running bills and deductions

The hard part on a long contract isn't making the bill. It's knowing, months later, what the department paid on each one and what it kept back. Keep a register per contract: RA bill number, date submitted, gross value, each deduction, net received, date and UTR.

GovtTenderHub's accounting tools keep that register for you. Make the GST tax invoice for each running bill, with CGST and SGST or IGST worked out and the amount in words. When a payment comes in, record what the department kept back: income-tax TDS, the 2% GST TDS, retention and other deductions such as labour cess. Reports show TDS by party and money still owed to you, and the deposit tracker shows security deposits still to come back. The free plan has 10 tax invoices a month; the Business plan has unlimited invoices (see pricing).

Common questions

What is the full form of RA bill?

Running account bill: the interim bill a contractor raises during a works contract for the work measured so far. It is also called a running bill, R/A bill or interim bill.

What is the difference between a running bill and a final bill?

A running bill is an advance for work done to date, and its quantities can be corrected later. The final bill settles the whole contract, and in CPWD no new claims can be raised after you submit it.

How many days does the department take to pay an RA bill?

In CPWD, at least 75% of the net bill within 10 working days of submission and the rest within 28 working days. If it's unpaid after 45 days and the bill is in order, 5% a year simple interest is payable.

What is deducted from a running account bill?

Usually income-tax TDS (Section 393, old 194C), 2% GST TDS on contracts over ₹2.5 lakh, security deposit or retention, labour cess where deducted, and recoveries of advances, materials or delay damages. The bill memo lists them.

What is a first and final bill?

A single bill that settles the whole work at once, with no running bills before it. In CPWD, works estimated at ₹20 lakh or less are paid this way, after completion.

Is an RA bill the same as a GST invoice?

No. The RA bill is the department's measurement-based payment form. If you're registered for GST, you also issue a tax invoice for the bill amount; printing the RA bill number on it makes the two easy to match.

Find tenders. Win them. Run the work.

  • Alerts, ₹299 a month: New tenders for your work by email every morning, anywhere in India, and full details of every tender.
  • Business, ₹599 a month: Alerts, plus who bid and who won each tender, GST bills, letters on your letterhead and workers' wages.

Searching tenders is free. Prices include GST; pay yearly and save 10%.

All guides

Trusted by contractors and suppliers across India